The building initiatives or building phasing for construction is directly related to the amount of funds available to the parish in any given time. The following is a broad-brush outline of building initiatives based on feedback given to us from the Building Committee on what their priorities for construction would be.

  • Purchase new Rectory (completed 2005)
  • Move out of existing Rectory
  • Construct meeting room additions, kitchen additions and storage additions to Activity Center
  • Demolish Waguespack conference room
  • Construct new administration building
  • Tie-in city water and sewer system
  • Provide restroom access from existing sanctuary to new restrooms in administration building
  • Construct new additions and renovate existing PSR building
  • Move into administration and PSR building
  • Demolish existing rectory
  • Construct new parking areas and promenade areas, including walkway and walkway covers
  • Construct new sanctuary
  • Tie into and renovate existing sanctuary to new gathering space
  • Renovate existing chapel